Namma Metro services on Mysuru Road to begin on March 26
Chiranjeevi Kulkarni
DHNS
Last Updated IST
Representative image. Credit: DH Photo
Representative image. Credit: DH Photo

Namma Metro services on Kempegowda Metro Station-Mysore Road (Reach 2) stretch will be restored from March 26, two days earlier than the schedule announced earlier.

On March 17, Bangalore Metro Rail Corporation Limited (BMRCL) had said that the train services on Reach 2 will be suspended till March 29 to take up signalling works on the Mysore Road-Magadi section as part of works to commission the extended line to Kengeri.

In a new release issued on Wednesday, however, Chief Public Relations Officer B L Yashavanth Chavan stated that the train services will be resumed from 7 am on Friday. This is due to the advance completion of signalling works on the section, he added.

ADVERTISEMENT
ADVERTISEMENT
(Published 24 March 2021, 20:01 IST)