×
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT

Polavaram project was pushed into deep uncertainty due to inefficient planning under YSRCP govt: Chandrababu Naidu

Releasing a white paper on the status of the project, Naidu said that Rs 12,157 crore is the likely cost of the completion of the balance works of Phase I of the project.
Last Updated : 28 June 2024, 15:34 IST

Follow Us :

Comments

Diversion of amount reimbursed to GoAP by GOI

Naidu also said that between 2014 and 2019 during the earlier TDP regime, an expenditure of Rs 11762.47 crore was incurred on this project by the state government, out of which an amount of Rs. 6764.16 crore was reimbursed to the state by the Government of India (GoI) during this period, and an amount of Rs. 4998.31 crore was pending for reimbursement, which was released subsequently after May 31, 2019.

Further, during the period from 2019 to 2024, in the previous YSRCP government regime, the state government incurred an expenditure of Rs. 4996.53 crore, even though the GoI reimbursed an amount of Rs. 8382.11 crore to the state government.

"Thus, an amount of Rs. 3385.58 crore was diverted instead of spending the same on the Polavaram project, thereby starving the project of funds. This has affected the progress of the works of the project and Land Acquisition (LA) and Relief and Rehabilitation (R&R) very badly, as payment of bills for an amount of Rs. 2697 crore is pending as of May 31, 2024. All the executing agencies of the project have practically stopped the work due to the non-payment of their pending bills,” Naidu said.

Only 3.4% of civil works completed between 2019 & 2024

Naidu also said that the progress of the civil works of the project during the period from 2019 to 2024 was only 3.84%.

"In respect of both the right main canal and the left main canal, practically no work was carried out during this period except clearing some pending payments. The works pertaining to the distributary network under the main canals have not yet commenced, and even DPR has not been finalised," Naidu said.

“Under the Land Acquisition (LA) and Rehabilitation and Resettlement (R&R) sectors also, the progress is meagre at 3.89 pc in this period. There was a drastic decrease in budgetary support for the project by the government of AP during 2019–24, when compared to 2014–19. In fact, the expenditure incurred on the project for the work done during the period from 2019–24 was Rs 4167.53 crore. There is also no tangible action regarding resolving disputes with Odisha, Chhattisgarh, and Telangana, getting approval for the 2nd revised cost estimate (at the 2017-18 price  level) etc,” he added.

He further said that, setting aside the advice from Polavaram Project Authority (PPA), the contracts of the executing agencies, namely M/s Navayuga Engineering Company Limited (NECL) and M/s Bekem Infra Projects Private Limited (BEKEM), were pre-closed and terminated, and later the works were awarded to Megha Engineering Infrastructure Ltd. (MEIL) by the Jagan government.

ADVERTISEMENT
Published 28 June 2024, 15:34 IST

Follow us on :

Follow Us